Critical path calculator
Run the critical path method on your own network: enter activities with durations and predecessors, get early and late dates, total float, and the zero-float chain that sets the end date.
Critical path calculator
Activities are labelled A, B, C in list order. Enter predecessors as letters, comma separated. Durations are in days.
| ID | Activity | Duration | Predecessors |
|---|---|---|---|
| A | |||
| B | |||
| C | |||
| D |
What this critical path calculator does
The calculator runs the two passes that define the critical path method. The forward pass computes each activity’s early start and early finish from its predecessors. The backward pass computes late start and late finish from the project end. Total float is the late start minus the early start: how many days an activity can slip without moving the project end date. Activities with zero float are the critical path.
The engine schedules dependencies with a topological sort, so the order you list activities in does not change the result. A dependency cycle or an unknown predecessor leaves an activity unschedulable; those are excluded from the results rather than silently reported as zero dates.
A worked example
Four activities: A, draft spec, 3 days, no predecessors. B, build, 5 days, after A. C, copywriting, 4 days, after A. D, launch, 2 days, after B and C. The calculator returns:
- A: early start 0, early finish 3, float 0
- B: early start 3, early finish 8, float 0
- C: early start 3, early finish 7, float 1
- D: early start 8, early finish 10, float 0
- Project duration: 10 days; critical path: A to B to D
Reading the float column
Copywriting finishes a day before it is needed, so it carries one day of float: it can slip a day and the launch date holds. Everything on the A to B to D chain has zero float, which is why it is critical: any slip there moves the end date day for day. That asymmetry is the management value of CPM. When someone asks to add scope, the float column tells you whether the work can absorb it and where the extra resource would actually help.
Why the critical path can change under your feet
The critical path is a property of the current durations and dependencies, not a label fixed at planning time. If copywriting takes three days instead of four, it has no float left and joins the critical path; if the build slips, its chain tightens. This is why teams re-run the pass weekly during execution. A path that was comfortable at kickoff is routinely the binding constraint by mid-project.
What CPM does not know
The critical path method works on single-point durations. It will tell you which chain is longest, but not how confident you should be in it: a ten-day critical path built on tight ranges is a different promise from one built on wide ones. Pair this calculator with the PERT calculator for uncertainty per activity, or with the Monte Carlo calculator, which samples every range across thousands of simulated runs and reports the distribution of possible end dates rather than one path.
From a static pass to a schedule that stays current
Inside Pocket PMO the same engine runs against your live project: dependencies come from the task plan or an imported Primavera P6 or Microsoft Project schedule, the pass re-runs when durations change, and the critical path feeds the forecast and the weekly status file. The calculator here is that screen with the project plumbing removed.
How to use this calculator
- Step 1
Enter each activity with a duration in days; rows are labelled A, B, C in order.
- Step 2
Enter predecessors per activity as comma-separated letters, for example A or B,C.
- Step 3
Calculate to run the forward and backward pass.
- Step 4
Read early and late dates and total float per activity; zero-float rows form the critical path.
Why the extra numbers matter
A single-point estimate hides its own uncertainty. These tools put the range on the table before the schedule is committed, which is exactly where it is cheapest to find out that a plan is optimistic.
- See the critical path on your own network in seconds
- Know exactly how much float each non-critical activity has
- Get early and late start and finish dates for every activity
- Same engine as the CPM screen inside Pocket PMO
Frequently asked questions
How is the critical path calculated?
With two passes over the network. The forward pass gives every activity its earliest possible start and finish; the backward pass, starting from the project end, gives the latest start and finish that still hit that end date. Total float is late start minus early start, and the activities with zero float are the critical path.
What is total float?
The number of days an activity can slip without delaying the project end date, assuming everything else holds. An activity with 2 days of float can start 2 days late; an activity on the critical path has 0.
Can there be more than one critical path?
Yes. When two chains both reach the end with zero float, both are critical, and a slip on either moves the project. Parallel chains with equal length produce this routinely.
Why is one of my activities missing from the results?
Activities that cannot be scheduled are excluded: that happens when a predecessor names an id that does not exist, or when dependencies form a cycle. Check the predecessor letters; they must match the row labels.
Does the order I list activities in matter?
No. The engine sorts dependencies topologically before scheduling, so results are identical regardless of list order. Predecessor letters refer to row positions, and rows are labelled A, B, C in the order you enter them.
Are lags, leads, or dependency types supported?
No. This calculator supports finish-to-start dependencies only, which is the case most estimates need. Pocket PMO itself works the same way for entered tasks; it is a deliberate simplification that keeps the schedule readable.
Keep going in Pocket PMO
In Pocket PMO the CPM engine runs on your live task plan or an imported P6 / MS Project schedule, re-runs when durations change, and feeds the forecast. The free tier covers it end to end.