Monte Carlo simulation calculator
Give every activity a triangular range, run 10,000 simulated schedules in your browser, and get the percentiles behind a defensible promised date. Nothing uploaded, nothing stored.
Monte Carlo calculator
Give each activity a triangular range (optimistic, most likely, pessimistic, in days) and finish-to-start predecessors as letters. The simulation samples those ranges 10,000 times and schedules the network each run.
| ID | Activity | Optimistic | Most likely | Pessimistic | Predecessors |
|---|---|---|---|---|---|
| A | |||||
| B | |||||
| C | |||||
| D |
What this Monte Carlo calculator does
For each run, the engine samples every activity’s duration from its triangular range, schedules the network through the dependencies, and records the project duration: the finish of the last activity. After 10,000 runs it reports the 50th, 80th, and 95th percentile durations, the mean, the standard deviation, the extremes, and a histogram of all simulated durations.
The percentile reading is the point. A P80 of 23 days means 80 percent of the 10,000 simulated schedules finished within 23 days. If you quote the P80 date and your ranges were honest, you will be late one time in five. Quoting the P50 invites coin-flip odds; quoting the average invites worse, because duration distributions are skewed, and the average sits above the most likely outcome.
How the sampling works
Each activity’s range is treated as a triangular distribution: the optimistic and pessimistic bounds are the corners, the most likely value is the peak. Values near the most likely are drawn more often than values near the corners, which matches how estimation uncertainty actually behaves. Sampled durations are rounded to a tenth of a day, then the network is scheduled finish-to-start through the predecessors you entered, exactly as the critical path calculator does for one pass.
The project duration of a run is the earliest finish of the final activity in that run’s schedule, which is how the dependency structure shapes the result: a wide range on an activity off the critical path gets absorbed by float, while the same width on a critical activity moves every percentile.
What the histogram tells you
The chart bins all 10,000 simulated durations. A single tall hump means the outcome is fairly predictable: the ranges are tight or the network is a simple chain. A long right tail means real schedule risk: a few pessimistic combinations push the end date far past the peak, and that tail is exactly what a promised date has to survive. Two humps usually mean a decision point in the middle of the plan that either goes well or does not.
How to read the inputs you should distrust
The simulation amplifies honesty and dishonesty equally. Ranges copied from a commitment (optimistic 5, most likely 5, pessimistic 5) produce a distribution with all of the risk and none of the visibility: every simulated schedule is identical. A useful sanity check is to run it twice, once with the ranges as argued and once with every pessimistic value halved; if the P80 barely moves, the end date is being driven by dependencies or by one dominant range, and that is where the conversation belongs.
When inputs need repairing, you will see it
If a range is entered out of order, say optimistic 6, most likely 3, pessimistic 2, the engine does not fail and does not guess: it sorts the triple and shows a note above the results saying it did. Negative durations are rejected with an error before any sample is drawn. Silent repairs are how simulation tools produce confidently wrong numbers, so this one reports every adjustment it makes.
Why 10,000 runs
Percentile estimates stabilize as runs accumulate: at a few hundred runs the P80 wanders by days between runs, at 10,000 it is stable to about a tenth of a day on networks of this size, and the whole run finishes in well under a second in a normal browser. The limiting factor for accuracy is the honesty of your ranges, not the run count.
From one simulation to a forecast that stays current
Inside Pocket PMO, this engine runs on your live project: tasks carry their ranges, imported P6 or MS Project schedules get default ranges you can tighten, and the forecast re-runs as work completes. The result is the sentence Pocket PMO exists for: the chance of hitting the promised date, and the few tasks that decide it. The calculator here is that engine with the project plumbing removed.
How to use this calculator
- Step 1
Enter each activity with optimistic, most likely, and pessimistic durations, in days.
- Step 2
Add predecessors as comma-separated letters (A, B, C in row order) to build the network.
- Step 3
Run the simulation: 10,000 schedules are generated and computed in your browser.
- Step 4
Read the percentiles: the P80 duration is the defensible promised date most teams quote.
Why the extra numbers matter
A single-point estimate hides its own uncertainty. These tools put the range on the table before the schedule is committed, which is exactly where it is cheapest to find out that a plan is optimistic.
- Get a completion percentile you can defend, not a single guessed date
- See the full distribution of possible project durations, not just the average
- Dependencies handled: every simulation schedules your actual network
- Same engine as the Monte Carlo screen inside Pocket PMO
Frequently asked questions
What is a P80 date?
The duration by which 80 percent of simulated schedules finish. If your activity ranges are honest, quoting the P80 means roughly one chance in five of being late. It is the conventional confidence level for schedule commitments in quantitative schedule risk analysis.
Which distribution does the simulation use?
A triangular distribution per activity, built from the optimistic, most likely, and pessimistic values you enter. Values near the most likely are sampled more often than values near the bounds. Triangular is the standard choice for three-point schedule estimates.
Are dependencies respected in the simulation?
Yes. Every one of the 10,000 runs schedules the network finish-to-start through the predecessors you entered, and the run’s project duration is the finish of the last activity in that schedule. Dependency order does not depend on the order activities are listed.
How long does the simulation take?
Under a second on a normal browser for typical networks. The run is synchronous in your own browser tab; nothing is uploaded, and no account is needed.
Why do the percentiles move slightly between identical runs?
The simulation samples random values, so two runs draw different samples and percentiles can differ in the last decimal. At 10,000 iterations the variation is a few tenths of a day at most. Use the trend, not the tenth.
Why does the calculator say it adjusted my inputs?
Ranges entered out of order are repaired before sampling: the triple is sorted, and the repair is listed above the results. Negative values are not repaired at all; the calculator rejects them with an error. Unreported repairs would silently skew the distribution, so this engine reports each one.
Keep going in Pocket PMO
In Pocket PMO the simulation runs on your living project, re-forecasts as work completes, and turns the percentiles into a weekly status file you can forward. The free tier covers it end to end.