PERT calculator
Turn optimistic, most likely, and pessimistic durations into expected durations, variance, and the chance of finishing by a target date. Runs in your browser, nothing stored.
PERT calculator
Enter optimistic, most likely, and pessimistic durations for each activity, in days.
| Activity | Optimistic | Most likely | Pessimistic |
|---|---|---|---|
What this PERT calculator does
For every activity you enter, the calculator computes the PERT expected duration, the variance, and the standard deviation. For the whole set it totals the expected durations and combines the variances into a project standard deviation. If you enter a target duration, it also gives the probability of finishing within that target using a normal approximation.
The formulas are the standard ones. Expected duration weights the most likely value four times as heavily as the extremes: E = (O + 4M + P) / 6. The variance is ((P - O) / 6) squared, so it depends only on how wide the range is, not where the most likely value sits. The standard deviation is its square root.
A worked example
Three activities, one chain: design, build, test. Design is estimated at 4 optimistic, 6 most likely, 14 pessimistic. Build at 3, 5, 7. Test at 2, 3, 4. The calculator returns:
- Design: expected 7.00 days, variance 2.78, standard deviation 1.67
- Build: expected 5.00 days, variance 0.44, standard deviation 0.67
- Test: expected 3.00 days, variance 0.11, standard deviation 0.33
- Project total: expected 15.00 days, variance 3.33, standard deviation 1.82
What the numbers are telling you
Design and build have similar most-likely durations, but design carries about six times the variance, because its range is 2.5 times as wide and variance grows with the square of the range: 2.5 squared is about 6.25. That gap is the whole point of PERT: the expected duration says what you plan for, the standard deviation says how much you should doubt it. When you add activities in sequence, the expected durations add, and so do the variances; the project standard deviation of 1.82 days is the square root of the summed variances, not the sum of the individual deviations.
Completion probability and the 50 percent point
The expected duration is the 50/50 point: with a target of 15 days on the example above, the calculator returns a 50 percent chance. A target of 16 days comes out at about 71 percent, and 18 days at about 95 percent. The calculator uses a normal approximation over the project standard deviation, clamped to 0 or 100 percent beyond three standard deviations. That curve is a simplification of real schedule risk, and it is a far more honest one than quoting the expected duration as a promise.
How to get a pessimistic estimate you can trust
The output is only as good as the range. The pessimistic value is not the worst imaginable case, it is the case where the usual things go wrong: the review finds real problems, the dependency slips a few days, the environment breaks. A useful check is the last time you did work like this. If the pessimistic value would not have covered that actual outcome, it is too tight. Activities where the team resists giving a pessimistic number at all are usually the ones that need the estimate most.
Where PERT falls short, and what covers the gap
PERT treats each activity independently and assumes the totals follow a normal curve. Real projects have dependencies that reshape the distribution, activities that correlate, and ranges that are not symmetric. The Monte Carlo calculator on this site covers the dependency part: it samples the full triangular range of every activity across 10,000 runs and schedules the network each time, which is the method to use when the number will be quoted to a customer. For a quick reading of one chain of activities, PERT is faster and usually close enough to start the conversation.
From a one-off calculation to a living estimate
Inside Pocket PMO, the same engine runs on your actual task list: activities convert to three-point estimates with sensible defaults you can tighten, the table stays in sync with the plan, and summary cards show total expected duration, project standard deviation, and completion probability next to a duration mismatch warning when the estimate drifts from the planned dates. The calculator here is that screen with the project plumbing removed.
How to use this calculator
- Step 1
List the activities you are estimating, one per row.
- Step 2
Enter the optimistic, most likely, and pessimistic duration for each, in days.
- Step 3
Enter a target duration if you want a completion probability, then calculate.
- Step 4
Read the expected duration per activity, the project total, and the chance of finishing within the target.
Why the extra numbers matter
A single-point estimate hides its own uncertainty. These tools put the range on the table before the schedule is committed, which is exactly where it is cheapest to find out that a plan is optimistic.
- Replace single-point guesses with three-point estimates
- See which activities carry the most uncertainty, not just the longest duration
- Get a completion probability for any target date, not just a single number
- Same engine as the PERT screen inside Pocket PMO
Frequently asked questions
What is the PERT formula for expected duration?
E = (O + 4M + P) / 6, where O is the optimistic, M the most likely, and P the pessimistic duration. The most likely value is weighted four times because it is usually the best-informed of the three estimates.
How is PERT variance calculated?
Variance = ((P - O) / 6) squared. It depends only on the width of the range: an estimate of 4, 6, 14 carries variance 2.78, while 5, 6, 7 carries 0.11, even though both have the same most likely value.
How does the calculator compute the chance of finishing by a date?
It converts the gap between your target and the expected total into a z-score by dividing by the project standard deviation, then applies a normal approximation, clamped to 0 or 100 percent beyond three standard deviations. At the expected duration itself the probability is 50 percent.
Can activity durations be in hours or weeks instead of days?
Yes. The calculator is unit-agnostic: enter all durations in the same unit and every result, including the target duration and probability, is in that unit. The labels say days because that is the most common case.
Why is my project standard deviation smaller than the sum of the activity deviations?
Because variances add, not standard deviations. The project standard deviation is the square root of the summed variances, which grows with the square root of the number of activities. Uncertainty partly cancels across a chain: some activities run long, others run short.
Is my data uploaded anywhere?
No. The calculator is a pure client-side component: your inputs go into a calculation function in your browser and nothing is sent to a server or saved.
Keep going in Pocket PMO
The PERT screen in Pocket PMO runs this engine on your whole task list, keeps the estimates in sync with the plan, and feeds them into Monte Carlo and the forecast. The free tier covers it end to end.