Work breakdown structure that feeds the forecast
Free while Pocket PMO is in beta. Break project scope into a work breakdown structure of manageable work packages, then keep that structure connected to estimates, risks, resources, and a P80 finish date.

Build your WBS, get a P80 finish date
The work breakdown structure is the scope. Give each work package an optimistic, most likely, and pessimistic duration and Pocket PMO runs those ranges through a Monte Carlo forecast. P80 is the finish that 80 percent of the simulated outcomes land on or before.
The published website-launch sample is five sequential work packages: Design review (3, 5, and 9 days), API build (8, 12, and 20), Data migration (5, 8, and 15), Frontend build (10, 14, and 24), and QA and launch (4, 6, and 11). Ten thousand checked outcomes from that sequence:
- P50 finish
- 51.1 working days
- P80 finish
- 55.4 working days
- P95 finish
- 59.6 working days
- Chance of a 50-day promise
- 41 percent
Download an Excel WBS template
The workbook is a worked website-launch work breakdown structure: phases, work packages, owners, and optimistic, most likely, and pessimistic durations in working days. The five work packages are the same sequence as the P80 example above.
Pocket PMO does not import this file. Use it to agree the tree with the people who own the work, then build that structure in the app. The guide explains how much detail to put on each row.
What a WBS generator is for
A work breakdown structure answers one question: what does finished look like, piece by piece? You take the project outcome and split it into deliverables, then split each deliverable into work packages small enough to estimate and hand to one owner. Done properly, the tree is the scope. Anything that does not appear in it is out of scope, and everything in it has a natural home for estimates, ownership, and progress.
A generator earns its name when the structure stops being a drawing. Codes assigned automatically, parents that summarize their children, and a tree that stays consistent while you add, edit, and delete nodes: these are the mechanical parts that spreadsheets handle badly, and handling them well is what lets you spend your attention on the decomposition itself. That is the job of the WBS screen in Pocket PMO.
Start from a template or a blank tree
Every project in Pocket PMO carries its own WBS. Pick a project template and the structure arrives preloaded, phases and packages already coded. Start blank and the first node you add becomes the root, numbered 1.0, with children numbered 1.1, 1.2, and so on. Codes are assigned for you and stay stable as the tree changes: add a child under 1.2 and it takes the next free number under that parent, even if you deleted siblings earlier, so gaps in the history never produce two packages wearing the same number. Editing a name or description happens in place on the node, and the change reaches every view that reads the structure.
Work packages, not wish lists
The discipline of a WBS lives at the leaf level. Packages with no children are marked as Work Package in the tree, which makes the planning review concrete: every leaf is a claim that this piece of scope can be estimated, assigned, and reported on. Nodes with children are summaries, and the tree shows their duration as a calculated roll-up instead of a number anyone typed.
That distinction does real work during planning. When a parent still shows only a calculated duration and no leaf packages beneath it, you have a phase wearing a deliverable costume. The tree makes those visible before they turn into estimating gaps in month three.

Durations that roll up while you plan
Each work package can carry a duration, and parent nodes compute theirs from the packages beneath them. At the project level, the calculated WBS duration feeds the estimate record automatically: add a package or change a number and the recalculated duration follows with no reconciliation step.
The roll-up shown on parent nodes is an additive total: each parent sums the durations of the leaf packages beneath it, a planning-level size of the work with no dependency awareness. The project duration is a separate calculation, a dependency-aware forward pass over the leaves the way a schedule engine would run it. Where packages have predecessors or run in parallel, that project duration comes out shorter than the summed parent totals, and it is the figure the estimate record takes. CPM and PERT build on the same package data, which is why a duration you correct once is corrected everywhere.
Describe the project, get a first draft
Facing an empty tree is its own kind of block, so the WBS screen has a Describe Project path. Paste a plain-language description of the project and Pocket PMO extracts tasks from it, builds the hierarchy, and opens the finished tree fully expanded for review. The draft is a starting point you will edit, and a better one than a blank screen: restructuring a generated tree is minutes of work, typing one from scratch is an afternoon.
Because the generated tree lands in the same structure as a hand-built one, everything downstream treats it identically: durations, estimates, and the schedule views all read from it.

One structure behind every analysis
The WBS in Pocket PMO is not a document that sits next to the estimates. It is the same record the PERT analysis, the CPM calculator, and the ROM estimator read from. Change the structure and the other views are notified and pick up the new tree, so there is no version of the plan where the WBS says one thing and the schedule says another.
The screen also keeps a running set of stats: total node count, count per level, and maximum depth. That is a quicker health check than it sounds. A tree one level deep is a to-do list; a tree five levels deep on a three-month project is a diary. Both show up in the numbers before they show up in a review.
Getting the structure out again
A WBS that lives only inside the planning tool eventually gets requested by someone with a steering committee, an auditor, or a scheduling standard. Pocket PMO exports the tree to PDF for the pack, Excel for anyone who wants to work the rows, and MS Project for teams that run detailed scheduling in another tool and need the hierarchy as their starting point. The exports carry the codes and hierarchy, so the structure survives the trip with its numbering intact, and they are generated from the live tree at the moment you click, never from a stale copy.

From structure to estimates
The tree is where estimating gets honest. Attach a three-point range to a work package and the estimate traces back to a concrete deliverable rather than a feeling about the whole project. Early on, while packages are still coarse, a ROM range at the package level keeps the conversation moving; as decomposition improves, firmer numbers replace the ranges on the same nodes, and the project estimate sharpens without being rebuilt.
This loop is what keeps a WBS alive past kickoff. The structure carries the estimates, the estimates expose which packages are still vague, and the vague ones tell you where to decompose next.
When the structure changes, everything follows
Scope moves on real projects: a package gets split, a phase collapses, a deliverable is dropped after a hard conversation. Delete a node in Pocket PMO and its subtree goes with it, roll-ups recalculate on the spot, and the views that consume the structure hear about it in the same moment. There is no second document to remember. That is the standard worth holding any WBS tool to: the tree is the one record of scope, and every edit is a planning event rather than a documentation chore.
A connected workflow, not another isolated file
Pocket PMO keeps project management techniques close to the rest of the project record so decisions can be based on consistent data.
- Turn high-level objectives into clear work packages
- Use a shared WBS as the source of truth for downstream planning
- Keep scope, estimates, owners, and delivery status aligned
- Refine package estimates with three-point and ROM ranges as detail improves
How teams use it
- Step 1
Start from a blank project or a reusable project template.
- Step 2
Create phases, deliverables, and work packages in a structured hierarchy — for example, Design → Interface specification → Approved wireframes.
- Step 3
Attach estimates and owners to each work package so the WBS feeds scheduling and reporting directly.
Frequently asked questions
What is WBS software?
WBS software helps teams break project scope into a hierarchy of deliverables and work packages so estimates, assignments, and reporting have one structure to hang on. In Pocket PMO the hierarchy is generated, coded, and rolled up automatically, and it feeds estimation, scheduling, and status reporting instead of living in a disconnected diagram.
What are the levels of a work breakdown structure?
Most projects do well with three: the project, its major deliverables, and the work packages under each deliverable. Apply the 100 percent rule at every level: the children taken together must capture all of the parent's scope and nothing outside it. Go deeper only where a package still needs several skills or vendors before one person can estimate and own it, because every extra level is depth you pay for in maintenance.
Is a WBS the same as a project schedule?
No. The WBS is deliverable-oriented and unordered: it says what exists, not when it happens. The schedule sequences the same packages over time using dependencies and durations. In Pocket PMO the two stay connected: durations live on the work packages, and the CPM view turns those, together with predecessors, into a sequenced timeline.
What is the difference between a work package and a task?
A work package is the smallest unit of the WBS that can still be estimated and owned as one deliverable. Tasks are the activities a package breaks into during execution. If a package needs a task list of its own before anyone can estimate it, it is not a package yet; decompose it one more level.
Can I import a WBS from Excel or MS Project?
Pocket PMO exports the WBS to Excel and MS Project, and creates structures from project templates or from a plain-language project description. There is no spreadsheet import for WBS rows. If you have an existing structure, the fastest path is usually generating a draft from a project description and reshaping it to match what you already have.
Can I keep the WBS in a spreadsheet instead?
You can, and many projects start there. The trouble arrives with the second document: estimates, schedules, and status reports all drift from the tree the moment someone edits a row and nobody propagates it. A WBS held in the same record as your estimates and schedule views cannot fall out of step with them, which is the whole reason to move it out of the spreadsheet.
Related planning pages
Work breakdown structure template guide
Learn how to structure a WBS template with phases, deliverables, work packages, owners, and estimate-ready details.
ROM estimates that feed the Monte Carlo forecast
Build a rough order of magnitude (ROM) range early, then refine into three-point estimates that feed the critical path and P80 finish date. Free while in beta.
PERT analysis software for schedule estimates
Estimate project schedules with optimistic, most likely, and pessimistic durations using PERT analysis in Pocket PMO.
Critical path method software for schedule control
Critical path software that identifies the activities, dependencies, and float that set your finish date, with CPM forward and backward passes built in.
See it in Pocket PMO
Pocket PMO keeps project management techniques close to the rest of the project record so decisions can be based on consistent data.