Schedule risk analysis tools, and which to pick when

Schedule risk analysis tools turn a single finish date into a distribution, usually with Monte Carlo, so you can see delivery risk before you promise the date. This page maps the public options fairly: enterprise suites, specialist desktops, and browser tools, and says which job each one is for.

Decision areaTypical alternativePocket PMO
DeploymentDesktop installs, enterprise licences, Excel add-ins, and a few browser toolsBrowser application, nothing to install
Indicative first-year costFrom $979/year (RiskyProject Professional) to ~$14,000+ (Safran Risk) at the enterprise end (published prices, October 2026). RunMonteCarlo publishes Pro at £99/year (10 November 2026).Free in beta; planned paid tiers are announced before they ship
Data it consumes.mpp/.xer and P6 schedules, Excel models, or a risk registerThree-point estimates you enter, a CSV, or a Primavera P6 (.xer) / Microsoft Project (.xml) schedule import
Who drives itOften a specialist risk analyst, model by modelA practising project manager, on the plan they already keep
Early detectionA periodic QSRA study, often once the date is already in doubtA P80 from three-point estimates and the critical path, before the promise is made
AI accessEarly vendor moves only: Lumivero’s @RISK Agent added an MCP connection in May 2026 (beta); none of these tools publishes a computation endpointOpen-source read-only MCP server (github.com/thepmexpert/pocketpmo-mcp): eight computation tools, runs locally

How to choose a schedule risk tool

Pick the tool that matches the question you are answering this week. A quantitative schedule risk analysis (QSRA) study for a governed programme is a different job from spotting, early, whether the date you are about to promise will slip. Desktop suites and browser tools both run Monte Carlo. They do not serve the same meeting.

Early detection of schedule delivery risk

Early detection means seeing the date risk before the status turns red. Estimate-driven Monte Carlo does that from three-point durations and the critical path, before work items have closed. A QSRA study does it later, and more deeply, on a governed schedule. Use the light tool weekly. Commission the specialist study when the audience requires it.

A fair method table

The rows are jobs, not scores. Each line says what the tool is for, and which neighbouring job it is the wrong shape for. Prices and product claims are copied from each vendor’s own site. Pocket PMO did not re-run their imports, their reports, or their correlation models. The public pages were read on 10 November 2026.

Schedule risk tools by the job they are for. Public positioning, observed 10 November 2026. Not a scored ranking.
ToolShapeBest whenDifferent job
Primavera Risk AnalysisEnterprise desktop QSRAP6-governed programmes that already buy through enterprise procurementYou need a weekly forecast the whole team runs
Safran RiskIntegrated cost and schedule risk suiteOil and gas programmes that need cost and schedule risk togetherYou need a lightweight browser forecast
Deltek AcumenSchedule diagnostics plus riskThe schedule needs a quality check before any risk number is trustedYou are replacing the weekly status cycle
RiskyProjectSelf-contained desktop suiteA named analyst wants Latin Hypercube and event chainsThe team has no Windows specialist
Tamara (Vose)Driver-based desktop modelYou want rapid modelling without building the schedule firstYou already maintain a full CPM network
Barbecana Full MonteMonte Carlo add-in for MS Project and P6You want Monte Carlo inside the scheduler you already useYou want a separate forecasting workspace
@RISKExcel Monte Carlo libraryThe model already lives in a spreadsheetYou need a project record the team shares
RunMonteCarloBrowser QSRA and cost riskP6 or MS Project users want a client-side P80 and a QSRA reportYou want a full project-management suite
CritovaBrowser suite with Monte CarloYou want boards plus P50 and P80 dates in one productYou want a forecast layer on a plan kept elsewhere
Pocket PMOBrowser forecasting layerA practising PM needs a P80 from three-point estimates and the critical path, early enough to change the promiseThe deliverable is a regulator-grade QSRA study or a task board

Browser peers: RunMonteCarlo and Critova

Two browser products sit beside the desktop list. Both descriptions come from their public sites, read on 10 November 2026. It is not a head-to-head: import fidelity, report depth, and correlation behaviour were not re-run here.

RunMonteCarlo (runmontecarlo.com), from Vantis Project Intelligence Ltd, describes quantitative schedule and cost risk analysis in the browser for planners on Primavera P6 and MS Project. Its public pages say the schedule stays on the device, that a free register includes a 2,000-iteration preview, and that Pro is £99 per year for the full Monte Carlo run, charts, and a QSRA report. Those are their published prices and claims.

Critova (critova.com) describes a project-management suite: boards, timelines, critical path, earned value, and Monte Carlo P50 and P80 dates. Its public homepage says every feature is free until 31 March 2027. A sample portfolio on that page shows a finish-date distribution. A forecast-only buyer may need only part of that suite.

UK writing says modelling. US writing says modeling. Both words mean the same method. Construction, capital, and infrastructure programmes are where specialist QSRA is common. Pocket PMO stays a forecasting layer for practising project managers. It does not claim to be a construction product, an infrastructure QSRA provider, or an enterprise P6 replacement.

The enterprise tier: Primavera Risk Analysis, Safran Risk, Deltek Acumen Risk

Oracle Primavera Risk Analysis is the incumbent: enterprise desktop deployment, the largest installed base, and over a decade as the reference for quantitative schedule risk analysis in P6-governed programmes; pricing runs through enterprise procurement. Safran Risk (~$14,000, published estimate at the time of writing, October 2026) dominates oil and gas, with integrated cost-and-schedule modelling, risk drivers, and weather windows. Deltek’s Acumen suite leads on schedule quality diagnostics: Acumen Fuse is the diagnostics product: it will tell you your schedule is not analyzable before it analyses it, and Acumen Risk adds the risk analysis layer (the combined offering runs ~$14,300 per three-year term, published estimate). All three assume specialist users, annual or multi-year commitments, and governance processes built around them.

The specialist mid tier: Lumivero SRA, RiskyProject, Tamara, Full Monte

Lumivero Schedule Risk Analysis (~$4,355, published estimate) takes an Excel-based approach familiar to estimation teams. RiskyProject from Intaver Institute ($979/year for Professional, published price) is the most self-contained desktop option: its own scheduling engine, .mpp/.xer import, Latin Hypercube Monte Carlo, and Event Chain Methodology, without requiring P6 or MS Project. Tamara from Vose Software (~$2,570, published estimate) is widely cited as the fastest tool in the category: driver-based modelling that skips schedule building altogether. Barbecana Full Monte is a purpose-built Monte Carlo add-in for MS Project and P6 schedules. These tools reward teams with a named risk analyst and a real QSRA practice.

The Excel library: @RISK

@RISK, from Lumivero (originally Palisade), is the most widely used Monte Carlo library in the industry: at its base it is an Excel add-in that brings distribution maths to whatever model you have built in a spreadsheet, and the @RISK Schedule Risk Analysis add-on extends the same engine to schedule work, importing Microsoft Project and Primavera P6 schedules. It is the right choice when your risk model already lives in Excel and your analysts are comfortable there, and with the schedule add-on it is a credible route into schedule risk analysis as well. Subscription pricing is published by Lumivero; verify current terms directly.

Where Pocket PMO sits

Pocket PMO is the lightweight browser tier of this market: PMI-standard methods (PERT three-point estimation, CPM critical path, Monte Carlo simulation, EVM) plus WBS, risk matrix, stakeholder management, budget tracking, and portfolio views, with nothing to install and a free tier, so you can verify the numbers before paying anything. It is not a deep QSRA suite: no event chains and no tornado charts, and a schedule import (Primavera P6 .xer or Microsoft Project .xml) drives the forecast through simplifications the import review flags, rather than a full desktop scheduling engine. It is for teams that need credible forecast numbers every week without buying the desktop or enterprise stack. The MCP server additionally exposes the computation core to AI agents as an open-source download; the closest incumbent step is Lumivero’s @RISK Agent MCP connection (announced May 2026, beta), which assists analysis workflows rather than publishing a computation endpoint.

Which tool, when

P6-governed capital programmes with existing enterprise procurement: Primavera Risk Analysis. Oil and gas with integrated cost-and-schedule risk: Safran Risk. Schedules of questionable quality that need diagnostics first: Deltek Acumen Fuse (paired with Acumen Risk when you go on to analyse). Excel-native estimation teams: Lumivero Schedule Risk Analysis or @RISK. A named risk analyst who wants a self-contained desktop suite: RiskyProject. Driver-based rapid modelling without schedule building: Tamara. MS Project or P6 users who want Monte Carlo inside their scheduler: Barbecana Full Monte. P6 or MS Project users who want a browser QSRA report at a published price: RunMonteCarlo, on their own public description. Teams who want boards, earned value and Monte Carlo in one suite: Critova, on their published launch offer. A practising project manager who needs the odds of a promised date from three-point estimates and the critical path, early enough to change the promise: Pocket PMO.

The honest limits of the browser tier

Choosing Pocket PMO means accepting real trade-offs, and naming them is more useful than pretending they are not there. There is no Event Chain Methodology, no tornado sensitivity charts, and no correlation modelling between activity durations (the PERT roll-up assumes independence, so correlated risks make the true spread wider than the tool reports). Schedule imports are read through a simplified view that the import review flags, not through a full desktop scheduling engine. Simulation iteration counts are tuned for interactive browser use rather than hour-long high-precision runs. If your deliverable is a defensible quantitative schedule risk study for a regulator or a bank, the specialist tier exists for exactly that, and the specialist tier is the right answer.

What the price tags actually buy

It helps to read the cost column as buying three different things. At the enterprise tier you are buying governance: audit trails, validated models, specialist support, and a vendor your procurement department already trusts. At the specialist mid tier you are buying depth: sampling methods, risk drivers, and modelling flexibility a generalist will never open. At the browser tier you are buying cadence: a forecast the whole team can run every week, connected to the schedule, budget, and risk data they already maintain. Teams that need all three genuinely buy all three; most teams discover they were only ever using one of them, and that the other two were line items, not capabilities.

Start free, on your own schedule

Whichever tier you pick, the input data is the same: an honest three-point estimate per task and a risk list with probability and impact scored. You can rehearse the whole discipline for nothing on the free tier: enter one project you know well as three-point estimates, run the critical path to see which activities actually constrain the date, then run the Monte Carlo and put the P80 date next to the deterministic one. The difference between those two dates is the simplest possible demonstration of what schedule risk analysis buys, and it costs nothing to see on your own data.

Questions to ask any vendor before signing

Whatever tier you evaluate, five questions separate the demos from the reality. What sampling method does the simulation use, and can you see and change the seed so runs are reproducible? How does the tool handle correlated durations, and what does it assume when you do nothing? What schedule diagnostics run before analysis, and what happens when a schedule fails them? What exactly does the export give you when the steering committee wants the numbers in their own pack? And what does the vendor themselves say is the tool not for? A vendor who answers the last question plainly is usually safe on the other four.

Frequently asked questions

Which schedule risk tool shows delivery risk early?

The earliest signal comes from the plan you already have: three-point estimates, the critical path, and a Monte Carlo P80, run before you promise the date. Pocket PMO is built for that weekly question. A QSRA suite such as Primavera Risk Analysis, Safran Risk, or RunMonteCarlo goes deeper when the deliverable is the risk study itself.

What is the cheapest way to start doing schedule risk analysis?

Free: enter your tasks as three-point estimates in Pocket PMO and run the Monte Carlo and critical path in the browser while the product is in beta. RunMonteCarlo publishes a free register with a 2,000-iteration preview, and Pro at £99/year (their site, 10 November 2026). Specialist desktop: RiskyProject Professional at $979/year (Intaver published price) or a Lumivero trial if your models live in Excel. Verify every price with the vendor. Buying an enterprise seat before you know whether a weekly browser forecast already answers the question is the expensive mistake.

Do I need Primavera P6 to do schedule risk analysis?

No. The desktop tools that integrate with P6 are aimed at P6-governed programmes, but Pocket PMO accepts a Primavera P6 (.xer) export directly, Microsoft Project plans via a save-as-XML export, or plain three-point estimates typed into the browser. The analysis maths (PERT, CPM, Monte Carlo) runs on whatever data you give it; P6 is a source, not a prerequisite.

What does P80 actually mean?

It is the date by which the simulated project finishes in 80% of runs: an 80% confidence date. In the sample project shipped with Pocket PMO's public MCP demo, the plan was 75 days but the simulated P80 landed near 90 days, meaning one run in five was expected to exceed even that. Reporting a single deterministic date hides this spread; reporting P50 and P80 together shows the steering committee both the median expectation and the date you can commit to with confidence.

Which tools support Event Chain Methodology?

RiskyProject, from Intaver Institute, is the notable desktop supporter of Event Chain Methodology among the tools listed here; the enterprise suites cover correlated risk drivers through their own modelling frameworks. Pocket PMO does not implement event chains, and we say so on every comparison page. If ECM is a hard requirement, that requirement picks your tool for you.

Is Pocket PMO a replacement for Safran Risk or Acumen Risk?

No. Those tools serve specialist quantitative risk practice: integrated cost-and-schedule modelling, sensitivity analysis, schedule diagnostics, enterprise governance. Pocket PMO serves the weekly forecasting cadence of a whole project team. Teams running a serious QSRA practice should keep the specialist tool and can still use Pocket PMO for the connected, every-week layer; the free tier makes trying both on the same project free.

Can AI agents run schedule risk analysis through these tools?

Two paths exist today, both early. Lumivero added an MCP connection to @RISK in May 2026 (beta) that assists analyst workflows inside their ecosystem. Pocket PMO publishes an open-source, read-only MCP server (github.com/thepmexpert/pocketpmo-mcp) that exposes PERT, CPM, Monte Carlo, EVM, portfolio roll-up, and risk scoring as callable tools to any MCP host, running locally on exported project data. The rest of the market has no published computation endpoint.