Migrating from Project Online: what retired, and an honest look at what comes next
Microsoft retired Project Online on 30 September 2026. This guide sets out what that means for PMO governance, what the designated successor does and does not cover, and the three migration paths in front of you, including where a dedicated forecasting layer fits.
What retired on 30 September 2026
Project Online was Microsoft's cloud portfolio and project management service. Microsoft retired it on 30 September 2026, and the planning, resourcing, portfolio, and reporting capabilities it hosted are no longer available. Microsoft published retirement guidance naming Planner as the path forward and documenting export routes for existing data. The retirement is not a rumour and not a marketing event: if your portfolio reporting depended on Project Online, those capabilities ended on that date, and every option below starts from that fact.
What the designated successor does and does not cover
Microsoft's designated successor is the newer Planner. For task execution it is a reasonable home: plans, tasks, assignments, and basic schedule views sit where your teams already work. For PMO governance the gap is material and worth stating plainly. Planner has no financial tracking or budgets. It carries a single baseline where Project Online offered eleven. And its portfolio oversight is thinner than what Project Online provided for cross-project resourcing, portfolio selection, and reporting. None of this makes Planner a bad product. It makes it a task-management successor, not a governance successor, and PMOs that try to run governance directly in it usually end up rebuilding the missing pieces in spreadsheets.
Path 1: stay in the Microsoft ecosystem, with Planner and manual governance
The lowest-friction option: let execution move to Planner and rebuild governance by hand, with budgets in spreadsheets, baselines captured as snapshots, and portfolio roll-ups assembled each reporting cycle. It works, many PMOs will choose it, and it keeps licensing and identity simple. The cost is recurring labour: every governance number is re-derived by copy-paste, every roll-up can drift from the plans it summarises, and whoever does the assembly becomes a single point of failure. If you take this path, standardise the spreadsheets before the first reporting cycle, because retrofitting structure onto a folder of personal workbooks is harder than starting with one.
Path 2: move to another Microsoft-stack portfolio tool
Microsoft's partner ecosystem includes portfolio and PPM tools that integrate with the Microsoft stack and cover part of what Project Online did: financials, resourcing, portfolio reporting. For organisations with procurement requirements, existing vendor relationships, or programmes that need deep resource management, this is a legitimate path worth evaluating on its merits. Score it against your actual governance requirements rather than feature counts: if the questions are budgets, baselines, and portfolio visibility, score exactly those. Expect enterprise pricing and an implementation programme; that is the trade for the depth.
What happens to the schedules you still have
A retirement does not erase the plans. Whatever you exported while the service was live, and whatever schedules still live in Microsoft Project or Primavera P6 files, survive as documents. Pocket PMO imports a Microsoft Project .xml export or a Primavera P6 .xer export directly: tasks, durations, and relationship details come across, including finish-to-start, start-to-start, finish-to-finish, and start-to-finish links with their lag. The forecast network itself uses finish-to-start links only and does not yet apply link lag, so CPM and Monte Carlo results can differ from the source schedule when it relies on other link types or lag. That matters more than it sounds, because re-entering a schedule by hand is where dependency mistakes get in quietly, and a forecast built on a mistyped network is worse than no forecast. If your saved Project Online export includes schedules you can still open in a scheduling tool, save them as XML and import; the forecast then starts from the plan that already exists.
Path 3: keep task execution where it is, add a dedicated forecasting layer
The third option separates the two jobs Project Online bundled together. Task execution stays in whatever tool your teams use, whether that is Planner, Jira, Asana, Smartsheet, or files, and a forecasting layer sits above it. Pocket PMO is that kind of layer, and we will be specific about what it is: a forecasting and governance workspace, not a task-management replacement. Teams enter three-point estimates, budgets, and risks, or load the schedule itself from a Microsoft Project (.xml) or Primavera P6 (.xer) export so the forecast starts from the plan that already exists; the app computes PERT expected durations, Monte Carlo delivery probabilities with iteration counts selectable up to 10,000, P50 and P80 finish dates, the CPM critical path and float, the EVM position, and probability-times-impact risk scoring. Nothing about your execution tooling has to change, so the migration stops being a replatforming programme and becomes an addition you can trial on one project in an afternoon.
Capability map: what Project Online did, and what covers it now
The table maps the capabilities PMOs actually used in Project Online to what covers them after retirement, and, where the claim is true, to the Pocket PMO equivalent. Where Pocket PMO has no equivalent we say so rather than stretch the mapping.
| Project Online capability | After retirement | Pocket PMO equivalent |
|---|---|---|
| Budgets and cost tracking | No native equivalent in Planner; typically rebuilt in spreadsheets | Project budgets with EVM cost tracking on the same project data |
| Baselines | One baseline in Planner, where Project Online carried eleven | No schedule-baseline store: Pocket PMO is a forecasting layer, not a baseline archive, so keep baselining in your schedule tool |
| Earned value reporting | Not provided; manual calculation in spreadsheets | EVM workspace computing standard earned value metrics, including CPI, SPI, EAC, and VAC, from budget and progress inputs |
| Portfolio dashboard | Per-plan views plus built-in cross-project roadmap views; no governance dashboard, so roll-ups are assembled by hand | Portfolio dashboard rolling up budget totals, risk counts, and RAG status across projects |
| Schedule forecasting (PERT, Monte Carlo) | Not provided | Core capability: three-point PERT sizing, Monte Carlo with iteration counts selectable up to 10,000, P50/P80 confidence levels, CPM critical path and float |
| Task execution | Planner's strength | Not replaced by design: execution stays in your existing tool; Pocket PMO holds the planning and forecasting layer above it |
Rebuilding the weekly reporting cycle
Project Online's reporting feeds ended with the service, so the weekly status pack needs a new source of truth. Pocket PMO generates the weekly status report from project data instead of hand assembly: it states the chance of hitting the promised date, a defendable P80 date, and the P50 and P90 finishes from the Monte Carlo run, in a file you can send to the steering group. That is the habit most PMOs lost on retirement day, and it is worth re-establishing in week one on a single project before trying to cover the whole portfolio. A report generated from one project record also cannot drift from the numbers it reports, which is the standing failure mode of the copy-paste cycle in Path 1.
How to decide
Three questions usually settle it. First, who assembles governance reporting today, and what does that assembly cost per cycle? Second, do your steering decisions actually depend on budgets and earned value, or only on dates? If the honest answer is dates only, Planner plus a lightweight roll-up may genuinely be enough. Third, how much migration programme can you absorb this year? Path 1 costs ongoing labour instead of a programme. Path 2 is a programme. Path 3 is an addition you can trial on a single project before committing anything. Whichever you pick, decide before the first quarterly report is due from the new estate, because that report is where improvised governance usually becomes permanent.
What the first week can look like
Day one: import one real schedule from a Microsoft Project .xml or Primavera P6 .xer export, or enter its tasks as three-point estimates. Day two: enter the budget and progress, then read the earned value position the app computes, including CPI, SPI, and the estimate at completion. Day three: run the Monte Carlo simulation and put the P80 date next to whatever date you had been promising. Day four: generate the weekly status file and send it to one steering group member instead of the usual spreadsheet. Day five: decide whether the numbers earned their keep. The trial is free while Pocket PMO is in beta, calculations run in the browser, and nothing about your Planner or file-based execution changes.
Frequently asked questions
What replaced Project Online?
Microsoft's designated successor is the newer Planner. It covers task execution, meaning plans, tasks, assignments, and basic scheduling, but it does not carry Project Online's financial tracking, its eleven baselines, or the depth of portfolio oversight. Governance capabilities have to come from somewhere else: spreadsheets, a Microsoft-stack portfolio tool, or a dedicated forecasting layer above your execution tool.
Is Planner enough for a PMO?
For task delivery, often yes. For PMO governance, usually not on its own: there are no budgets or cost tracking, only a single baseline, and portfolio reporting across many plans is thin. If your steering committee only asks whether work is on track task by task, Planner can carry it. The moment reporting needs budgets, earned value, or cross-project risk and probability, plan for a governance layer beside it.
What happens to my Project Online data?
After 30 September 2026, Project Online projects and their data are no longer accessible through the service. Microsoft's documented export routes applied to data saved while the service was live: a previously saved export still holds your records, including schedules, tasks, and resourcing history, but anything that was not exported before retirement cannot be pulled out of the retired service now. What any export gives you is records, not governance: budgets, baselines, and earned value reporting have to be re-established in whatever you choose next. If you did not export before the retirement date and need to discuss recovery options, contact your Microsoft account team, and check Microsoft's official retirement guidance for the current specifics rather than relying on third-party summaries.
How do I keep earned value reporting after the retirement?
EVM needs three inputs that have to live somewhere: a budget, a progress record, and a schedule. Spreadsheets can carry it if the discipline holds, but hand-maintained EVM calculations drift easily. Pocket PMO computes earned value metrics from the budget and progress data entered on each project, so EVM reporting continues without a Project Online subscription, and the portfolio dashboard rolls budgets and risk position up across projects.
Do I have to move my teams off Planner?
No. Pocket PMO is a forecasting and governance layer, not a task-management replacement, and it does not touch how work is assigned day to day. Teams keep executing wherever they are today, whether that is Planner or anything else, and the forecasting layer reads the schedule through a file import or three-point estimates you maintain. There is also no tenant to provision and no per-seat rollout, because nothing changes in the tools your teams open every morning.
What does Pocket PMO cost after Project Online's retirement?
Nothing while Pocket PMO is in beta. Paid tiers are planned but not live yet; when they ship they add cross-device forecasts, weekly file history, and cloud backup. There is no server infrastructure to stand up in the meantime because calculations run in the browser, so the cost of a trial is the afternoon you spend on one real project.
Run the example on your own schedule
Trial the forecasting layer free in Pocket PMO: PERT, Monte Carlo, CPM and EVM on one real project, with the maths shown.